Bid leveling vs tender levelling: the same job, different words
Bid leveling (US) and tender levelling (UK, Middle East, Australia) are the same job: putting every bid on the same scope so they can be compared fairly. The words differ, such as bid tab for levelling sheet, plugs for adjustments and scope sheet for pricing schedule, and US packages are more often priced as lump sums against a scope of work than item by item against a pricing schedule.
The terms, side by side
- Bid leveling → tender levelling
- Adjusting every return to a common basis. US spelling uses one L.
- Bid → tender return or priced return
- A supplier's or subcontractor's priced offer.
- Bid tab → levelling sheet
- The spreadsheet with every bidder side by side.
- Scope sheet or scope of work → pricing schedule
- The list of what's being priced. A BoQ adds measured quantities.
- Plug or plug number → adjustment
- A figure added for scope a bidder left out.
- Exclusions and clarifications → qualifications
- What a bidder left out or assumed.
- Alternates → alternatives or options
- Priced variations on the base scope, outside the tender sum.
- Allowances → provisional sums
- Fixed amounts carried by every bidder for work not yet defined.
- GC and subs → main contractor and subcontractors
- The contractor running the job and the trades pricing packages.
What actually differs
- Itemised pricing: UK tenders on a pricing schedule are often priced line by line, so levelling happens item by item. US bids are more often a lump sum with a breakdown, levelled scope item by scope item.
- Quantities: a UK BoQ gives quantities for everyone to price; US bidders usually do their own take-off.
- Rules: UK practice draws on NRM, Australian on ASMM, and Gulf projects often on POMI or NRM with FIDIC contracts; US practice depends more on the owner's and GC's own procedures.
The method is the same
- Put every bid on the same list of scope.
- Check the bidders' sums.
- Add plugs (adjustments) for missing scope and take out what wasn't asked for.
- Price the exclusions and clarifications.
- Compare the leveled (levelled) totals, not the bid amounts.
With TenderNorm
TenderNorm works with either: upload the pricing schedule or scope sheet, then the bids in the bidders' own Excel or PDF formats. It lines every price up against those items, checks the sums and flags what's missing or changed. Projects can be priced in pounds, US, Australian and other dollars, euros, dirhams, riyals and more.
Questions
- Is it leveling or levelling?
- Leveling in US English, levelling in UK English. Same word, same job.
- What is a bid tab?
- The US name for the spreadsheet showing every bid side by side, the UK levelling sheet.